Friday, May 27, 2011

W1D5

Started the day under rain.Saw how workers remove the form-work while waiting for the rain to stop. New floor has been set up at Section 3 when i was off yesterday.It was almost all the same for today by doing the inspection for Section 1 which is to be concreted.Will have to perform inspection of beam and slab for Section 2 on tomorrow as well as the shear wall of Section 3 for level 36.After tomorrow,my first week of intern is done and i will have to start with my weekly report.